Climent Rental
Climent Rental
Climent Rental
Case Studies

A Temporary Chilled Building for Logistics Operations

A Temporary Chilled Building for Logistics Operations- How This Packing Area Was Delivered in Under Three Weeks

To construct a temporary chilled building for a food packaging operation.

client one icon

CLIENT

Chilled Logistic Operation

client two icon

INDUSTRY

Chilled Logistics

client three icon

SOLUTIONS

Temporary Chilled Building

client icon

TOTAL KW

600kw cooling- 10x 50kw LT AHUs

Operations

temporary Chilled Building- The Challenge

A great job this one.

 

We were approached to offer a rapid solution for a chilled packing area. Large in size, and to be built within an existing warehouse, the area was to be used for chilled storage and packing of box meals.

 

A very tight schedule of 3 weeks to completion was required to meet a contract start date. With this in mind, a rapidly built structure and cooling system was required. The proposed contract duration was 35 weeks with costed options for extension.

A temporary building under construction
A temporary building under construction. The aluminium frames are assembled on the ground before being lifted into position.

The Solution to a Temporary Chilled Building

After initial meetings and discussions, an insulated 25x100mt structure was proposed with a 600kw glycol cooling system. A modular Aluminium framed structure was fitted.

 

Supplied flat packed, the building was assembled on-site. Superior insulation was achieved with 80mm PIR wall panels and inflatable membrane roof. For rapid installation, a modular cooling system was fitted with 3 external glycol chillers and 10 internal 50kw low temperature AHU’s. A rubber hosing system with Camloc connectors was used for glycol distribution.

 

In the photo, construction of the building can be seen. The Aluminium support beams are assembled on site and lifted/ fixed into position. Following-up behind, the wall and roof panels are then installed. Built in 5mt bays, the building can be extended to any size.

Summary

We really love jobs like this.

From initial customer contact to hand over, delivery was achieved in under 5 weeks. All the customers requirements were met and they were able to start operations on-time. It really shows what can be achieved when a motivated customer meets a “can do” contractor.

The project to date has been in operation for 3 months. Modifications have been made internally to the building, with areas partitioned to suite ongoing needs. Another key advantage to this temporary solution.

A completed temporary building on hire located in a larger warehouse space
Temporary Building for logistics
Internal shot of the completed building. The low temperature AHU's can be seen to the side. Ten were fitted in total to maintain a 4 degree holding temperature.

The completed temporary chilled building. In the background the low temperature AHU’s can be seen.

 

Fitted their own lifting frames, the AHU’s are designed to be portable. Significantly, for rapid install, they include a controller and glycol cooling valve.

Temporary cold storage glycol chillers
The external glycol chillers. In the foreground the 400kw chiller and to the rear the 2x 150kw chillers. Modular rubber hosing was used for distribution.

The external plant- 2x 150kw and 1x 400kw glycol chillers.

 

To ensure reliable operation of the chilled building three separate cooling systems were installed. In this way, the failure of any one system would not compromise operation. Modular rubber hosing can be seen running away from the units.

5 key advantages of hiring a temporary chilled building;

  1. Rapid installation from stock.
  2. Fixed weekly payments that are fully offset able against gross profit
  3. No capital outlay or depreciation costs on capital equipment.
  4. All servicing and breakdown costs are met by the rental company.
  5. Flexibility, modifications to the structure and cooling system can be made easily.

 

For further information on our temporary building cold storage services please click here

Get your FREE estimate

24Hr Help. Now free from mobiles.

When calling please have the following ready:

  • Your Name
  • Company Name (If applicable)
  • Site Post Code
  • Problem you’re having
  • Email Address

    RELATED INDUSTRY SUCCESS STORIES

    Temporary Fruit Coldstore in Kent For a Major Packer

    Temporary Fruit Coldstore in Kent For a Major Packer

    A really nice temporary chilled storage project. This fruit storage warehouse was finished to a high specification and has been contracted initially for 2 years.

    A Temporary Chilled Logistics Building for Food Distribution

    A Temporary Chilled Logistics Building for Food Distribution

    To provide a major distribution company with a temporary chilled logistics building. A really good job this one, with an interesting problem to solve.

    Additional Cold Storage Capacity for a Major Flower Distributor

    Additional Cold Storage Capacity for a Major Flower Distributor

    Cold storage is especially tricky to maintain in readiness for the six or seven weeks of the year when you really need it. Renting equipment when you really need it makes business sense.

    Temporary Cold Storage in Scotland. The Scalloway fish market in Shetland

    Temporary Cold Storage in Scotland. The Scalloway fish market in Shetland

    ACR were very proud to have been chosen to carry out this strategic project for Shetland Island Council. This project was a slow burner from the-off, with multiple visits to the Island, many options were discussed until the final solution was arrived at.

    Turning a Warehouse into a Temporary Coldstore

    Turning a Warehouse into a Temporary Coldstore

    One of the larger warehouse cold storage conversions we have carried out. From the initial proposal to final commissioning and ongoing support, this project ticked all the boxes for us and a very happy client.

    Left Menu Icon
    ×